Commissioning building systems
Commissioning refers to the process of bringing an item into operation and ensuring that it is in good working order. On building projects, this refers primarily to building services.
When, after all or part of a fixed building service or on-site electricity generation system has been installed, replaced or altered, the system is taken from a state of static completion to working order. Testing and adjusting are carried out for fixed building services, as necessary, to ensure that the whole system uses no more fuel and power than is reasonable in the circumstances. Testing and adjusting are carried out for on-site electricity generation systems, as necessary, to ensure that the whole system produces the maximum amount of electricity that is reasonable in the circumstances For each system, commissioning includes all of the following.
|
Building services requiring commissioning may include:
- Heating, cooling and ventilation systems.
- Generators.
- Switchboards.
- Water supply and sanitation.
- Pumps.
- Motors.
- Fire detection and protection systems.
- Information and communications technology (ICT) systems.
- Security systems.
- Facilities management systems.
- Process plant.
- Lifting equipment and escalators.
- Acoustic and vibration appraisals.
The contract documents should set out:
- Who will be responsible for commissioning different building services.
- What methods, standards and codes of practice are to be used.
- What should happen to test results.
- Whether commissioning is to be witnessed and if so, whom.
- The documentation that is required.
Commissioning can benefit from the preparation of a commissioning plan, which according to BSRIA Guide BG 8/2009 Model Commissioning Plan should:
- Provide general information about the project.
- Identify the commissioning team members for each stage of the commissioning process.
- Define roles and responsibilities for each commissioning team member.
- Identify the systems to be commissioned.
- Create a schedule of commissioning activities for each stage of the process.
- Establish documentation requirements associated with the commissioning process.
A commissioning manager may be appointed to give advice during design, construction planning and installation and then to manage commissioning, testing and handover.
Commissioning activities may include:
- Ensuring client access and providing client training and demonstrations.
- Completing operating and maintenance manuals, record drawings, software and test certification.
- Obtaining statutory approvals and insurance approvals.
- Manufacturers work testing.
- Component testing.
- Pre-commissioning tests.
- Set to work: this is the process of switching on (i.e. setting to work) items such as fans and motors to ensure that they are operating as specified (for example checking that fans are turning the right way).
- Balancing: this follows setting to work and involves looking at whole systems (rather than individual components) to ensure that they are properly balanced (i.e. water is coming out of all the taps at the correct pressure, air is coming out of the correct diffusers, etc).
- Commissioning checks and performance testing.
- Post commissioning checks and fine tuning during occupancy.
NB: The building regulations require that a commissioning notice is given to the relevant building control body (BCB) confirming that commissioning has been carried out according to a procedure approved by the Secretary of State. See Commissioning notice for more information.
The BSRIA guide to 'Commissioning Air Systems' (BG 49/2024), written by by Keith Barker and published by BSRIA in March 2024, explains how to commission ducted air distribution systems in buildings. It was originally published in 2013, then 2015 with the latest update in 2024. For the benefit of the guide and number of commissioning relate terms arte defined, some of which are included here for information:
- Commissionable system: 'A system designed, installed and prepared to specified requirements in such a manner as to enable commissioning to be carried out'
- Commissionability: 'The ability of a system to be functionally tested and regulated satisfactorily'
- Commissioning: 'This is defined in CIBSE Code M[6] as "A process of assuring that a project is planned, programmed, costed, designed, installed, tested and fine-tuned, so it meets specified performance requirements".
- Commissioning management: 'The planning, monitoring and control of all aspects of commissioning and the engagement of all those involved in it, to achieve the specified outcomes.'
- Commissioning manager (CxM): 'The entity that leads the management of the commissioning process on a project.'
- Commissioning specialist: 'The organisation or person appointed to carry out specified duties in connection with functional testing and regulating of systems.'
- Commissioning specification: 'The document (or sub-section of the design specification) that prescribes the detailed objectives and requirements for commissioning Note: the specification should refer to drawings, schedules and relevant parts of the codes, manuals, guides and other standards.'
[edit] Related articles on Designing Buildings
- BREEAM seasonal commissioning.
- BSRIA Water Treatment for Closed Heating and Cooling Systems BG 50/2021.
- Client commissioning.
- Commissioning documents.
- Commissioning notice.
- Commissioning plan.
- Commissioning planning.
- Commissioning report.
- Commissioning v testing.
- Corrosion in heating and cooling systems.
- Handover to client.
- IAQ developments accelerated by COVID-19 pandemic.
- Initial commissioning case studies.
- Inspection.
- Migration strategy.
- Practical completion.
- Seasonal and continuous commissioning.
- Soft landings.
- Specialist commissioning manager.
- Training for pre-commissioning cleaning of pipework systems.
Featured articles and news
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Comments